We are upgrading three different Water Treatment Plant Filtration systems in Golden Bay (Collingwood, Pōhara and Upper Tākaka).
Works include:
Current status | Delivery |
Start Date | Construction Early 2025 |
End date | Construction end May 2026 |
Access | N/A |
Contractors | Process Flow |
Cost | $103K |
Email [email protected] for further information.
We have projects set up to look and improve these existing treatment plants to reduce impact on the environment and meet modern standards.
We are starting with Collingwood, Tākaka and Motueka and improving their Secondary Treatment Systems by investigating the work required and engaging special expertise.
We are looking at nutrient loading, decreasing solids and stormwater flows in all three plants, as well as reducing nitrogen and ammonia that is produced.
Current status | In design |
Start Date | Construction March 2025 |
End Date | Construction end March 2026 |
Access | N/A |
Contractors | Not yet appointed |
Cost | $TBC |
Email [email protected] for further information.
Update May 2024
Work on the upgrade of Golden Bay’s Port Tarakohe is progressing well.
The more than $12 million dollar project has been made possible through a $6 million loan from Kanoa, the provincial development investment group within the Ministry of Business, Innovation and Employment, which is on top of the $6.7 million we have identified to invest in the 2024/2025 year.
A new fuel bowser has been moved to a new site at the end of the floating wharf making it easier and more convenient for vessels to refuel.
The new large berths are getting their finishing touches and the inner breakwater to offer increased wave protection has been completed.
Work on a new sheet pile wharf on the northeastern arm is underway and design work for new offices and an ablution block is being done.
Meanwhile, the long-term vision for the port is being developed with iwi, key stakeholders, recreational users, and the community to produce the Port Tarakohe Structure Plan.
Drafting of the plan is being done ahead of community engagement before the year’s end.
For more information on the Structure Plan, visit shape.tasman.govt.nz/port-tarakohe-structure-plan.
Port Tarakohe upgrade work started July 2023
This project comprises of three stages:
Stage One: Breakwater extension
This includes a breakwater extension of about 20m, ending in a sheet piled wall. The existing breakwater of about 125m length will also be widened. These works include supplying new materials and reusing some of the existing ones. Since the breakwater and surrounding areas are Little Penguins Habitat, a major aspect of this Separable Portion is the compliance with the Penguin Management Plan. The successful Contractor will work closely with the Penguin Experts and Department of Conservation to ensure the safety of penguins during the works.
Stage Two: Fendering Upgrade
This work is to remove the existing worn-out fendering system on the concrete wharf and replace with a new sleeker design. This work will have to be completed at low tide and in good weather. The project involves removing some 60 piles; supply and installation of about 90 piles and new materials, and reuse of some of the existing materials where needed. The works will be completed in a way that allows 1/3 of the wharf to be always operational.
Stage Three: New Pontoons adjacent to new breakwater extension
New pontoon berths and new piles will be installed. These include removal of existing piles and plastic pontoons, driving several new piles, installation of concrete pontoons and an end wave barrier, and service pillars’ installation. The Contractor shall provide access to existing berths’ users during the duration of works.
Update July 2024 - Works Complete
The Takaka Annex Internal refurbishment project is underway soon, and it will become a new Hydrology Satellite office for operations in Golden Bay. We also received approval to undertake an internal upgrade to set up the building with office with storage spaces and a lab area with an accessible toilet. We look to complete this June 2024.