We installed a new section of watermain on the southern side of Bird Lane, to supplement the pre-existing watermain. The new larger (150mm diameter) section of watermain is approximately 300 meters long and runs along side the existing pipeline route. The pre-existing pipe was connected to the new watermain and acts as a feeder line into some properties.
The pre-existing pipe was not large enough to service growth and was too small to provide sufficient water flows required for fire fighting. The upgrade also means a more reliable water supply and less disruption to residents if there are any problems with either pipe in the future.
|
Start date |
October 2019 |
|
End date |
November 2019 |
|
Access |
For short periods, vehicle access to some properties may need to be restricted and the water supply will be interrupted for a few hours when the new watermain is put into service (mid-November). |
|
Contractors |
Ching Contracting Ltd. |
|
Contract cost |
$145,000 |
Click on the map to view a larger version.
The highlighted line shows the route of new watermain that was installed
Contact the project manager Alistair Stevens by phone on 03 543 8400 or by email: projects@tasman.govt.nz